Reviewing and qualifying the ageing management activity

Attributes of adequate ageing management programmes are defined by the regulation; see for example the NUREG-1801 (US NRC, 2010) adapted by several VVER operating countries. An adequate AMP has to have the fol­lowing elements:

1 Definition of SSCs that are subject to ageing management

2 Actions to prevent or mitigate specific ageing processes

3 Surveillance, monitoring and testing of all parameters related to the deg­radation of the function or serviceability of the SSCs

4 Investigation of ageing factors that may cause degradation or loss of function of SSCs

Building or part of the building

Structure

Aim of the monitoring

Measurements

Evaluation and criteria

Main building complex: Reference points all buildings, including reactor and auxiliary buildings, stacks, diesel-building and other structures

Building

movements; settlement; contro of stability of cracks caused by movements

Fixed geodetical measuring points; I

3D evaluation of building movements; correlation with groundwater table; allowable declination of vertical axis of reactor pressure vessel defined by functioning of CRDM

Reactor building: floor

Heavy reinforced

Interaction with

Investigation of

Control of mechanical and chemical

slabs and walls

concrete

boric acid media

samples; inspection of check-holes

properties and comparison with reference values

Reactor building,

Reinforced

Control of possible

Investigation of

Control of mechanical and chemical

turbine building, intermediate building and galleries: floor slabs and walls

concrete

leakages and

consequent

leaching

samples; inspection of check-holes

properties and comparison with reference values

Reactor building: floor slabs and walls

Carbon steel liner

Control of

corrosion rate, identification of possible leakages

Ultrasonic control of liner wall thickness at the identified places

Control of corrosion rate and thickness; focused investigation if the overall leak tightness is less than the reference value for the given unit (comparison with allowable leak rate)

Reactor building and auxiliary building: floor slabs and walls

Decontaminable coating and painting

Control of condition of coating and painting

Walk-down and visual control according to checklist

Expert judgment

Main building complex: all building parts

Hatches, gates, penetrations, fire protection doors;

Control of condition of doors

Walk-down and visual control according to checklist, fluorescent test

Expert judgment

 

Подпись: ©Woodhead Publishing Limited, 2013

5 Trend analysis to predict degradation processes and to perform correc­tions in time

6 Acceptance criteria to assure that the functions of the SSCs are maintained

7 Correction measures to prevent or solve problems

8 Feedback process to ensure that preventive actions are effective and appropriate

9 Administrative control of the processes

10 Information retrieval from operational practice to ensure that ageing management is properly carried out.

The same attributes can be applied while reviewing the adequacy of existing plant programmes.