Как выбрать гостиницу для кошек
14 декабря, 2021
Scope
An operating rule limit on coolant gas pressure is set, based on vessel integrity at specified temperatures:
• Excess coolant pressure is a trip parameter indicative of overfilling or severe boiler tube failure, the boiler operating at a higher pressure than the reactor.
• Rate of fall of pressure is a reactor trip parameter on magnox stations indicative of a depressurisation, for example, caused by a failure of the pressure vessel or circuit.
• Low coolant pressure is also a trip parameter.
• Rate of rise of coolant pressure is drawn to the attention of the operator as an alarm and he may decide to trip the reactor manually.
Typical trip settings are given in Tables 3.5 and 3.6. Magnox reactors
For reactors with steel pressure vessels, a coolant pressure limit based on vessel temperature will be set such that an adequate margin on vessel integrity is maintained if a shock loading was to occur. This limit is normally in the form of a graph of vessel pressure against minimum vessel temperatures, where safe conditions are to one side of a line on the graph.
Pressure Accurate measurement of the reactor gas circuit pressure is provided to enable the operator to comply with the station’s Operating Rules. In the case of Berkeley, a digital display of reactor gas pressure is prominently positioned on a panel in the CCR with individual gas circuit pressures indicated on the eight boiler/blower panels. The digital display unit also has high and low pressure alarm features to attract the operator’s attention to significant changes from the desired level. A recorder situated in the CCR annex also provides information about trends in pressure changes and is a reliable back-up to the CCR indications. An extremely accurate bourdon tube pressure gauge, which is directly connected to the pressure vessel and situated in the reactor blower/ boiler control room, is used by the plant attendant when changes in gas pressure are required for operational purposes. This is a useful instrument as it is independent of all electrical supplies and therefore the operator can verify the reactor pressure at any time without difficulty. A high reactor gas pressure trip system is installed which is part of the safety
Table 3.5 Protection, alarm and trip settings /or a typical magnox reactor
|
circuits and also a warning alarm set just below the
trip lev cl.
Level of reserves The Berkeley power station Operating Rules require a minimum level of 61 t of CO: to be kept in reserve for reactor coolant duty. The station’s storage capacity of 213 t of CO: is far in excess of the minimum required, but for operational requirements, this higher level is maintained as far as is practically possible. There are no direct indications in the CCR of CO: stored, but stock control is administered by the CCR supervisor who orders direct from the supplier, A daily record of CO; stocks taken from direct-reading indicators on the storage tanks is kept by the CCR supervisor and CO; usage is controlled by the operator. This method of stock control
T xBt. E 3 6
Typical AGR (ripping schedule
Trip parameters |
Trip setting nominal |
Redundancy |
C omments |
||
Main guar dime |
|||||
1 |
Pulse count rate htah ties el onl>) |
500 1ЛЧ- |
2 out of 4 |
||
2 |
Plus period (log DC l |
24 ч iJoahiing time 2n,] |
2 out of 4 |
||
3 |
Excess flux (linear channelsi rate and lex el stop |
200 MW min up 1000 MW nun down Q margin lO^o (40 MW min} |
2 out of 4 |
||
4 |
Excess flux (log DC channels — from linear output} rate and level stop |
Upper 1" MW |
2 out of 4 |
||
5 |
Low reactor pressure 1 |
28.5 bar a |
2 out of 4 |
||
6 |
Low reactor pressure 2 |
28.5 bar a |
2 out of 4 |
||
7 |
High reactor pressure 1 |
44.8 bar a |
2 out of 4 |
||
8 |
High reactor pressure 1 |
44.8 bar a |
2 out of 4 |
||
9 |
High CGO temperature rate and level stop |
10°C min up 200°C/min down Q margin 40°C Upper 7|0°C |
2 out of 4 in each case of two separate sets |
||
10 |
High circulator outlet gas temperature rate and level stop |
7°C/min up 7°C/min down Q margin 20°C Upper 320°C |
2 out of 4 |
||
11 |
Circulator undervoltage |
Less than 3.3 kV for greater than 200 m/s |
Two 2 out of 4 |
||
12 |
!GV position |
14° |
1 out of 2 per quadrant into 2 out of 4 |
||
13 |
Any one quadrant extra high circulator outlet gas temperature |
370°C |
2 out of 3 per circulator |
||
14 |
High boiler half-unit outlet gas temperature (via quadrant trip initiated) |
320°C |
2 out of 3 per halfunit into 1 out of 6 per quadrant into 2 out of 4 |
||
15 |
Circulator underspeed (via quadrant trip initiated) |
2520 r/min |
2 out of 3 per circulator into 1 out of 2 per quadrant into 2 out of 4 |
||
16 |
High CACS demineralised water temperature (via quadrant trip initiated) |
40°C |
2 out of 3 per quadrant into 2 out of 4 |
||
17 |
Two quadrant trips initiated |
— |
2 out of 2 |
||
18 |
Safety room high temperature |
40°C |
2 out of 4 |
||
19 |
Impact vibration |
10 dВ above background |
2 out of 4 |
||
2U |
fuelling maG. me grab load |
U LI 1880 kg U — L2 2)80 kg O-‘L 2775 kg ROC 80-85 kg/s |
2 oul of 3 |
||
21 |
Pile cap air lemperaiure high |
130°C |
2 out of 4 |
Distributed sets. Channel trip if one thermocouple rises 30° above ambient of 50° noting two series thermocouples to one input. Local gas temperature at trip 80°C nominal. |
T fil t 3.6 icontd)
Typical AGR tripping schedule
Гир parameters |
Trip ‘Citing nominal |
Redundancy |
Comments |
Dnc’e — juardhne j H і e h COO temperature rattr. ми! e ■ e! ‘top |
Identical to Item 9 — main guardline |
2 out of 4 |
|
3 hvcC’S lT. iv Circaґ Jt. mr. eNt rate and level v;op |
Identical to item 3 — mam guardline |
2 out o; 4 |
|
3 Quadrant trip initiated |
— |
2 out of 4 |
|
Auxiliary guardline I Pulse couni rate high |
>U0 kW |
2 out of 4 |
|
Quadrant protection I Half-unit outlet gas temperature high, loss |
320°C 2‘0°C |
2 out of 3 per halfunit into 1 out of 6 per quadrant |
Safety U"Ociaied |
2 Low superheater transition joint metal temperatures |
See Note l |
2 out of 3 per halfunit into l out of 6 per quadrant |
|
3 Circulator underspeed.’overspeed |
2520 r/min 3220 r^min |
2 out of 3 per circulator into 1 out of 2 per quadrant |
Safety a-oociaied |
4 Differential oil pressure across circulator bearings very low |
0.75 bar |
2 out of 3 per circulator into 1 out of 2 per quadrant |
|
5 Oil level from circulator compartment very high |
See Note 2 |
2 out of 3 per circulator into I out of 2 per quadrant |
|
6 Circulator lub oil tank level very low |
See Note 2 |
2 out of 3 per circulator into 1 out of 2 per quadrant |
|
7 Circulator high differential pressure between reactor and motor compartment |
4 bar |
2 out of 3 per circulator into 1 out of 2 per quadrant |
|
8 CACS demineralised water temperature high |
40° C |
2 out of 3 per quadrant |
Safety associated |
9 Circulator outlet gas temperature high SSD initiation |
435°C |
2 out of 3 per circulator into l out of 2 per quadrant |
|
Bulk group 1 insertion |
69^0 |
||
Delay timer |
4.35 s |
S’oies
1 Trip >eiting is a function of steam pressure
2 Trip is based on integral level switches with fixed setting
3 {,) = quiescent
ihen enables the operator to have a reasonable assessment of CO: reserves at any time and is able to ensure that minimum levels are maintained.
Shutdown action — coolant pressure There are automatic reactor trips on high pressure and high rate- ol-ehange of pressure.
To cater for maximum credible depressurisation faults on steel pressure vessel stations, emergency shutdown devices (ESD) are installed. These shutdown devices are individually tripped on high rate of change of pressure, independently of the guard lines. The rapid shutdown is to guard against coincident core distortion caused by the depressurisation fault.
Tvpical values Berkeley Hinktey Роті.-1 Oldbury
Normal operating pressure, bar ’.’9 12."5 25.17
High pressure trip, bar 7.93 13.38 26.34
High oP’6i, bar/min 0.68948 2.07 4.%
{The above are illustrative only, the pressures may be measured at different parts of the gas circuits.)
AGRs
Reactor gas pressure Apart from maintaining a coolant pressure to permit adequate fuel cooling, there are also important safety implications:
• Reactor pressure failing at higher than the usual rate to be expected from normal vessel leakage implies some breach in the primary circuit pressure boundary. The assessment is facilitated by an on-line calculation of mass of gas in the vessel, based on measurements of reactor pressure and temperature.
• High reactor pressure implies that either there is a boiler leak or the CCb admission valve is not closed when it should be. This prompts operator action to isolate the leaking boiler or close the CO2 valve,
• It is necessary to ensure that the reactor is not overfilled prior to the start of power operation.
Pipework is installed so that reactor gas pressure can be measured at four points under the vessel top slab, one in each quadrant above the boiler annulus. The pipework is 17.2 mm o. d. and 3.2 mm thick stainless steel. The pipework for each quadrant is routed through the quadrant instrument penetration at the + 2.3 m level and thence to the quadrant outer reactor gas instrumentation racks.
For quadrants A and D there is a transducer, giving a 4-20 mA signal for a range 0-60 bar with an accuracy of 0.5%. For quadrant В there is a low pressure range transducer giving a 4-20 mA signal for a range 0-6 bar with an accuracy of 0.5%, The pipework from quadrant C is not used, being isolated by a valve in the primary isolation valve rack at the +3.9 m level and capped in the quadrant outer gas instrument rack.
The signals from quadrants A, В and D are used
as follows:
Indication-alarm Quadrant signal used
CCR unit desk high range indication A
CCR unit desk ІО’л range indication В
CCR diree(-wire facia low pressure alarm (via A, D
alarm amplifier set at 32 bar) (grouped)
CCR direct-wire facia high pressure alarm A. D
(via alarm amplifier set at 42.5 bar) (grouped)
CR post-trip mimic analogue indication D
CCR post-tnp mimic low pressure digital signal A, D
LIC panel indicator В
НІС post-trip mimic analogue indication A
Valves are provided to enable the transducers and alarm amplifiers to be calibrated and tested while the reactor is at power.
All signals are also fed to the data processing system.
The pipework, transducers, alarm amplifiers and cabling are aseismic. Gas pressure reactor trip signals are not derived from this equipment.
Gas baffle dome pressure differential This is important for safety in three respects:
• High gas baffle dome pressure differential indicates the approach towards the limit of design pressure differentia! plus the margin allowed in the design code.
• Reduced limits on gas baffle dome pressure differential must be observed during refuelling to ensure that partially withdrawn fuel sleeves are not subjected to excessive tensile stress due to internal pres — surisation or buffeting due to excess gas cross-flow.
• Low gas baffle dome pressure differential may indicate that the gas flow over the fuel elements is insufficient for adequate cooling and, in particular, the flow may not be sufficient to give proper CGO thermocouple response and hence may render reactor protection from CGO temperature signals ineffective.
In the case of Heysham 2, the pressure differential across the gas baffle dome is measured at four points, one in each quadrant of the reactor.
The pipework is 17.2 mm o. d. and 3.2 mm thick stainless steel, and is used solely for differential pressure measurement; no gas sampling flows are drawn down the pipework since this would affect the differential pressure measurement. The pipework from each measuring point is routed through a different penetration for each channel, i. e., the relevant quadrant instrument penetration at the +2.3 m level.
There are four transducers measuring the pressure differential, one in each quadrant outer reactor gas instrumentation rack, approximately 6.5 m above the instrument penetration and about 3.5 m from the vessel wall. The accuracy is 0.5% full-scale with a range of 0-4 bar and they are designed for operation at up to 60 bar static pressure.
Each channel provides a 4-20 mA signal. The signals from quadrants A and C are sent to the data processing system. Those from quadrants В and D are fed to a 2-way switch on the unit desk in the CCR so that either may be displayed on the conventional indicator on the desk.
Additionally, alarm amplifiers on quadrant В and D channels generate alarms for high gas baffle dome differential pressure {at least 2.70 bar). These are grouped to give a single direct-wired facia alarm in the CCR and are individually repeated to the data processing system. Valves are provided to enable the transducers and alarm amplifiers to be calibrated and tested while the reactor is at power.
The data processing system derives alarms from the analogue signals from quadrants A and C in the event of abnormally high and low values.
The pipework, transducers, alarm amplifiers and cabling are aseismic.