Как выбрать гостиницу для кошек
14 декабря, 2021
13.22. The Combustion Engineering design evolved from that of the three-unit Palo Verde Generation Station in Arizona, which began commercial operation in 1986. A summary of design specifications for the proposed system is given in Table 13.2. The format follows that used in Table 13.1.
13.23. The fuel assemblies are in a 16 x 16 array with rod dimensions similar to those used in the Westinghouse core. However, as seen in Fig. 13.6, there are five large thimbles in each assembly. Four of these are for control rods and one for instrumentation. There are clusters of both four and 12 elements in the core. The 12-element cluster spans five assemblies. Each rod cluster is connected by a “spider” to the drive mechanism. Groups of these clusters are moved as units for power regulation. Burnable absorber rods are substituted for fuel rods in the lattice, as needed, rather than inserted in the control rod thimbles.
13.24. The reactor cooling system arrangement is shown in Fig. 13.7. Four circulating pumps serve two large steam generators. The steam generator secondary-side water inventory has been increased by 25 percent to improve the response to upset conditions and to extend the time available for countermeasures should the feedwater supply be interrupted. Similarly, the pressurizer volume has been increased by 33 percent to reduce the pressure changes during transients such as reactor trip and load rejection.
13.25. The reactor operating margins relative to previous designs were increased by the foregoing improvements as well as by a reduction in the hot-leg temperature and improved monitoring methods. Also, the new design provides for carrying out operating power level maneuvers using control rods only. Thus, the need for short-term boron-level adjustments is reduced.
13.26. Numerous other evolutionary design features contribute to simplification and improved safety margins. A probabilistic risk analysis indicated a reduction in the risk of severe accidents by two orders of magnitude compared with that for present systems.
|
|||||||||||
|
|
|
|
|
Fig. 13.7. System 80 + ® reactor coolant system showing improvements (© 1989 Combustion Engineering, Inc.). |
13.27. A 61-m (200-ft)-diameter spherical containment for this system provides both safety and cost advantages. As shown in Fig. 13.8, a concrete shield building encloses an inner steel sphere which has a relatively large internal free volume of 9.5 x 104 m3 (3.4 x 106 ft3). The steel shell acts as a heat sink and the large volume provides energy-absorbing capability in the event of an accident. An in-containment refueling water storage tank (IRWST) combines the functions of a refueling water tank and a post — LOCA containment sump. Economic advantages also result from efficient space utilization and ease of construction.[27]
13.28. To control costs, this and other new reactor proposals feature extensive standardization, not only for the Nuclear Steam Supply System, but the entire plant. This is in accordance with NRC’s standardization rules given in 10 CFR 52, which also provides for design certification so that the plant can be pre-licensed prior to purchase. A 48-month construction period is estimated, which should help meet a construction cost goal for new plants established by EPRI of $1500 per kW(el).
Fig. 13.8. Elevation view of System 80 + ® spherical containment (© 1989 Combustion Engineering, Inc.). |