Development of an improved installation procedure and schedule of RVI modularization

1.5 Development of an improved installation procedure for RVI modularization

Under the existing installation procedure, six snubber shims were assembled between the RV core-stabilizing lugs and the CSB snubber lugs after alignment of the CSB and the RV. Subsequently, assembly and flexure welding of the LSS and the CS were conducted. The new and improved installation procedure for RVI modularization was developed allowing assembly and flexure welding of the LSS and the CS to be performed before the main installation process. Alignment of the CSB assembly and the RV and assembly of the snubber shims were undertaken during the main installation process.

The improved installation procedure for RVI modularization (Ko, 2011) appears in Table 4 as order 1 and order 3. A detailed explanation is given below of the flexure welding of the LSS and the CS in the CSB as well as of the alignment and installation of the snubber shims of the CSB assembly and the RV.

Order

RVI installation procedure

Remark

1

Assembly of the LSS and the CS in the CSB, Flexure welding

Improvement

2

Welding of the flow baffle in the RV

3

Alignment of the CSB assembly and the RV, Installation of snubber shims

Improvement

4

Installation of the CSB assembly in the RV

5

Installation and alignment of the UGS

6

Installation and alignment of the RV head

7

Installation of alignment keys, dowel pins and guide lugs insert

8

Final alignment, Installation of head down ring and HJTC tube

Table 4. Improved installation procedure for RVI modularization

1.5.1 Alignment of the CSB and RV and calculation of the dimensions of the snubber

shim

1. The dimensions between the RV outlet nozzle and the reactor coolant loop (RCL) were measured after the welding of the RCL. They were recorded along with the measured dimensions before the welding. The widths of the RV core-stabilizing lugs were also measured.

2. The measured positions were marked on RV keyways and the relative positions of the keyways on the RV centerline were measured using the widths and vertical degrees.

3. The target-hole positions of the RV flange on the RV centerline and the dimensions of the gauge blocks of the RV core stabilizing lug were also measured. Here, the dimensions of the required measurements were the heights and widths of the gauge blocks.

4. Before installation of the gauge blocks, the integrity of the RV core-stabilizing lugs and the cap screws was checked. Neolube was applied twice on both the threaded surfaces on the cap screws and the surfaces of the bearings.