Bale loading into racks at the SSL

Ideally, the bale — loading — into — racks operation at the SSL should be able to load 16 bales in a rack in 20 minutes. This design criterion has not been attained with actual equipment.

For a workday with 10 productive hours (600 min), a 20-min-per-rack operation can theoretically load 30 racks, or 15 truckloads. Given the reality of SSL conditions, an actual operation could not sustain this productivity. In this analysis, it is reasonable to assume that a mature operation can average 70% of the theoretical productivity. The number of loads — day-operation used for this analysis will be reduced to 15*0.7 = 10.5 loads/d. The number of individual SSL operations required is 315 loads per week, divided by 6-day SSL operation per week, which is 52.5 or 53 loads per day average operation. This is five operations averaging 10.5 loads per day.

Thus, loading operations will occur at five different SSLs with a different set of equipment for each operation. Each SSL operation will load an average of 21 racks per day. Time to move the crew, equipment and reposition the empty trailer/rack from one SSL to the next is not dealt with in this analysis. Thus, the 21 racks/d productivity may be optimistic.

There are several options to load the rack. The option which found to be the most cost effective is the "side-load" option [58]. A telehandler with special attachment can pick up two bales per cycle (Figure 15) and load these bales into the side of the rack. Assuming that the average productivity to be achieved under production conditions is 34 min per rack, then the time needed to load two racks on a trailer is 68 min. Remember, this is the assumed average load time for year-round operation.

image57

Figure 15. Concept for side loading bales into rack on trailer.

At the SSL, loading of the racks is the most challenging design for a cost-effective biomass logistics system. It is difficult to reduce the cost of these operations because the labor productivity (tons handled per worker-hour) might be low. By uncoupling the SSL loading and highway hauling, the truck does not have to wait for racks to be loaded in order to pick up the trailer. Also, the SSL crew does not have to wait for a truck to arrive with empty racks. However, the hooking/unhooking of trailers may be problematic for some drivers.

The day-haul operations are uncoupled by providing two extra trailers at the "day haul" SSL, and the night-haul operations are uncoupled by providing 9 extra trailers for the "night haul’ SSL. Each truck tractor then has 11 extra trailers (22 racks) in the system. This may not be a best (least cost) approach, but it does provide a reasonable starting point.