Construction steps

4.1 Facility layout

The anaerobic digestion can be accomplished in one digester, and thus the facility is called ‘single-stage biogas facility’. In other facility layouts, the anaerobic digestion can be carried out in two stages, i. e. in two different tanks in order to optimize the operating conditions, and thus the facility is called ‘two-stage biogas facility’. The single-stage facility is a simple design with a longer track record, and has lower capital costs and technical problems. The two-stage facility has shorter retention time as each stage design is optimized. There is a potentially higher biogas production from two-stage facilities, but they require higher capital costs.

Subsequent to the site investigations such as the soil specifications ground water level, the facility layout should be planned. The commercial biogas plants consists of a fermenter and a secondary fermenter or so called "follow-up fermenter", where both have identical dimensions, usually as follows: height of 6 m, internal diameter of 23 m, and external diameter of 23.70 m. This implies that the thickness of the fermenter wall is usually 35 cm. A residue storage tank is annexed to the fermenters, where the tank has an internal diameter of 25 m, external diameter of 25.70 m and a height of 6 m (Fig. 4). The solids feeder is located adjacent to the fermenter, and the tanks are surrounded by green belt from all sides except one side where the horizontal silos are located.

First Stage Second Stage

image180

image181

(b) General process scheme of the two-stage anaerobic digestion process (Blumensaat and Keller, 2005)

(c) BIOGAS NORD GmbH

4.2 Dimensions marking

The marking of dimensions (Fig. 5) for biodigester unit should be performed prior to start of excavation work. The marking is considered as preparation for excavation and construction works. An operational area of 3 m width around the digester should be considered, where the workers will use this area to achieve the construction works around the tank base in order to prepare the structure of the concrete base, i. e. the bottom of the digester.

image182

Fig. 5. Marking of dimensions for a biodigester

4.3 Excavation works

The depth of digging depends on the specifications of the soil. The inclination of the sides should be 30 cm for each meter depth for the cohesive soil, 60 cm to one meter for the light soil, and 90 cm for the sandy soil.

image183

(a, b) BIOGAS PLANT DESIGN

The bottom of the pit should be concave, where the center of the digester should be the most concave. Generally, the pit shape depends on the design of the digester, where in the case of round-shaped household units (Figs. 6a and b) a guide wood post is installed in the center of pit bottom. A string is linked to the post and used to set the round-shape of the pit. On the other hand, in the case of commercial biogas plants (Fig. 7), total station, teodolit or laser leveling is used for surveying. For large digesters, i. e. for commercial biogas plants, bulldozers are used to achieve the excavation (Fig. 7).

image184

Fig. 7. Excavation works for a commercial biogas plant

4.4 Preparation of the digester’s bottom

The pit’s bottom should be cleaned, and the gridiron is built (Fig. 8) using a pre-selected type of iron rods as either 606 m-1 or 608 m-1. Subsequently, the concrete mixture is poured (Fig. 9 and 10). The water:cement ratio is 0.53 L kg-1 and the cement:sand:gravel mass ratio is 1:2.2:3.7. The thickness of the concrete base ranges between 10-25 cm depending on the soil’s specifications and the ground water level.

image185

Fig. 8. Structuring the grid irons for a commercial biogas plant (MT-ENERGIE GmbH & Co. KG)

image186

Fig. 9. Pouring the concrete mixture for a commercial biogas plant (BIOGAS NORD GmbH)

image187

Fig. 10. Concrete bottom of a household unit 5.5 Building the digester

In case of commercial biogas plants, the digester is huge as its diameter may reach 25 m; therefore, the concrete structure should be reinforced (Fig. 11). Hence, the iron rods are used to build 2 iron grids to reinforce the digester wall starting from the digester bottom plate. The standard length of iron rods is 12 m. The standard iron rods are cut to shorter iron rods, and they are then used to build up the tank. Subsequently, either wood panels or pre­constructed metal sheets are used to enclose the iron grids and to form a container for the fluid concrete. When the digester wall is built, about one third of the internal wall of the tank is covered by a protection layer in order to protect the internal face of the wall against corrosion.

image188

Fig. 11. Building the digester wall for a commercial biogas plant

In case of household units, burnt-clay bricks are used to build the digester (Fig. 12) and they should be able to tolerate a pressure up to 100 kg cm-2 owing to the fact that the walls of the digester are exposed to the pressures of the soil and the moving equipment near to the digester. A mortar of cement and sand mixture by 1:4 is used. The construction works are followed up till the appropriate height, and the entry or exit holes of the pipes are blocked by a filling material.

image189

Fig. 12. Building the digester wall of a household unit using burnt-clay bricks 5.6 Integrating the heating tubes

Building the digester is associated with integrating the heating tubes. Building the wall starts with structuring the iron grids which will be encased by wood panels or pre­constructed metal sheets, and before pouring the concrete, the heating tubes should be integrated (Figs. 11 and 13). The heating tubes are made of polyvinyl chloride (PVC), inside these tubes hot water flows to heat the digester. The water temperature is either 35 oC or 55 oC depending on the used bacteria as either mesophilic of thermophilic bacteria, respectively. On the other hand, in other designs the heating tubes are installed on the internal surface area of the digester wall.

image190

Fig. 13. Integrating the heating tubes (BIOGAS NORD GmbH)