Как выбрать гостиницу для кошек
14 декабря, 2021
The typical checks that are given in the following paragraphs are those that may be required for either дОК or magnox power stations. For a wide description it is considered that the starting point commences with the reactor vessel depressurised, filled with air and all control rods except the safety group inserted. It is also assumed that all plant commissioning checks and tests have been completed. The following are typical of the basic requirements the operator will need to be satisfied about before he proceeds to prepare the plant for start-up:
• Relevant maintenance and testing work completed on all available plant.
• Access to pressure vessel sealed and all joints made.
• Radiological de-zoning due to shutdown removed.
• All relevant safety documents (safety rules fourth edition and radiological) cleared and cancelled. All isolations removed and plant ready to set to work.
• Safety circuits — trip and alarm levels restored to required values for start-up and safety line trip setting certificate received from the instrument engineer.
• Temperature scanners alarm settings restored to normal for normal reactor operation.
Once satisfied on the above general activities, he will then proceed proper to the pre-start-up phase_and will consider the following:
• Boiler and feed system — minimum number of boilers to be totally available as specified in the operating instructions.
• Circulating water system — all systems in service with the required items of plant available.
• Main water treatment available and reserve feed — water tanks full with water at the correct purity for operation.
• Pressure vessel cooling system in service with water at correct purity.
• Sufficient gas circulators available as specified in the operating procedure and all commissioning schedules completed.
• All pressure closures (fuelling and control rod standpipes) seated in the correct position.
• Fuelling machine available for service.
• Emergency generator available as specified in the Operating Rules.
Having been satisfied that the above items are complete, carbon dioxide can be admitted to the vessel. During filling to the design density, checks will be made on the pressure circuit for leakage and any other abnormality.
The points of interest are leakage from the follow ing:
• Any pressure flange or dome at its joints.
• Pipework which has connection to the pressure vessel or boilers, e. g., oil pipework on circulator, major valve lands and standpipe assembly closures.
If these checks ave satisfactory then proceeding to the start-up is commenced. During this period, immediate:) prior to commencing the withdrawal of control rods, the following checks are made:
• That correct carbon dioxide purity is achieved (the maximum quantity of air is not exceeded — this is achieved by successive purging).
• That safety circuits, counter channels, flux channels and alarm systems are correctly set, active and in service.
• That temperature scanners are in service.
• That instrumentation is calibrated and in service.
• That burst cartridge detection equipment is in service and sufficient systems are available to satisfy the Operating Rules.
• That control rods are in the correct start-up position and the sequence interlocks of control rod movement are checked and proven.
• That the reactor trip function operates and all electrical supplies are cut off from the control rod mechanisms.
When all the physical checks are completed on plant and equipment then it is necessary to satisfy technical considerations of limiting temperatures within the reactor core and vessel. The temperatures which are significant and must comply with the limits as imposed by the Operating Rules are:
• Pressure vessel temperatures (concrete for concrete pressure vessels plus differential temperatures between adjacent zones).
• Liner temperature (concrete pressure vessel).
• Fuel temperature (specifically for magnox reactors).
• Moisture in coolant gas (water or hydrogen in
CO:).
• Bulk reactor gas outlet temperature.
If all the above considerations satisfy the operator, the operating instructions and the Operating Rules then reactor start-up to criticality may proceed. Criticality should be achieved close to the prediction, but if this does not occur {i. e., criticality is too soon or does not occur within ±200 milliNiles), then the sequence must be stopped and investigated. Criticality prediction is discussed in Section 5.2 of this chapter.
Start-up checks during approach to power During the approach to criticality close observation of all operating parameters is essential. All control rods in the same groups should move in line and the difference in height between rods in the same group should not vary by more than a few inches.
The most critical and potentially hazardous phase is at the approach to criticality. This is because the deep penetration of rods produces criticality low down in the core. Since most of the instrument thermocouples are housed in the top of the core, deviation of temperature at the bottom can be obscured from the operator. It is necessary for the operator to be extremely vigilant at this time. At criticality the power level will be flattened-off at about 100 kW thermal to allow the operator to make a true assessment of the conditions within the reactor before proceeding.
The first control of the coolant composition is by applying a strict specification for the supply of carbon dioxide and methane. The CECB specification for liquid carbon dioxide purity is as follows:
sorption of CO2 in alkali hydroxide solution shall not exceed 100 vpm in the completely vaporised material. |
Methane is a colourless flammable gas and is the first member of the alkane series of hydrocarbons. It is soluble in alcohol and ether and slightly soluble in water. It is the major component of natural gas and is normally shipped as a compressed gas or occasionally in bulk as a cryogenic liquid. It is used in the production of ethanol, methyl chloride and methylene chloride. It is not considered a toxic gas but acts as an asphyxiant.
Oxygen is a colourless non-flammable gas essential for combustion, vigorously oxidising many elements directly at room temperature or aboe. it is slightly soluble in water and more soluble in organic solvents. It is used in many industries including iron blast furnaces, glass manufacture, ТіСЬ production and in the direct oxidation of ethene to ethylene oxide. Oxygen is normally produced by the liquefaction-distillation of air and is supplied both as a gas and a liquid. Argon and oxygen are not completely separated by this process because of their relative boiling points. The argon under irradiation will transmute to the radioactive Ar-41 and hence oxygen for magnox and AGR use is produced elect го I у t icall у to minimise the argon concentration.
Carbon dioxide is used by many industries and’is supplied to the CEGB in liquid form, being delivered to each station in road tankers. It is stored in refrigerated and insulated vessels at a pressure in excess of reactor operating pressure. The liquid is evaporated by passing the carbon dioxide through a steam jacketed heater and passed to the reactor through reducing akes.
The specification for the methane supplied to the
reactor is:
Maximum permitted concentration 20 ppm
Impurity Water Other
Hydrogen farbon monoxide Carbon dioxide r^her impurities Not specified Not specified Not specified Sub vpm |
Impurity Maximum permitted concentration
20 vpm 1 vpm 1 vpm (total) 10 vpm
Nil
I vpm 100 vpm Not specified Not specified Not specified
The methane used in an AGR can be supplied from two sources; either manufactured on site or delivered to site as a compressed gas or in liquid form. In both cases care has to be exercised in the transport of the methane to the main circuit due to its explosive properties when mixed with air. The flammability limits for methane are 5-15.4 Vo in air. This may invoke the safe routing of pipework, the use of double pipe tubing or its dilution with an inert gas (carbon dioxide) to below the lower explosive limit and the adequate ventilation of rooms through which the gas is transported.
The method of manufacture on site is by electrolysis of water using conventional electrolysis plant to form hydrogen and oxygen. The hydrogen is washed to remove alkali carryover and is mixed with either the stoichiometric or an excess quantity of carbon dioxide and passed over a two stage 0.5°!) ruthenium on an alumina support catalyst bed maintained at a temperature of 350°C. Between the two stages is a cooler/ drier to remove moisture and to increase the effluent methane concentration from typically 49 Vo after the first stage to 60 ‘/о (dry volume) after the second stage (less than 5 Vo effluent hydrogen concentration). The gas is then dried and compressed to above reactor pressure for transfer to the reactor gas coolant. The above processes follow* the following chemical reactions:
2H20 2H; + Cb and 4H2 + C02 CH4 + 2H2O.
The primary advantage of this process is that the requirements for methane and oxygen (excluding the small imbalance due to reactor leak rate and carbon monoxide production from graphite corrosion) is met from a readily available source, namely water, which is exactly balanced by the water removed in the drier system. The disadvantages of the process are the costs and difficulties associated with constructing and op — erating/maintaining a chemical plant compared to the much reduced initial costs of installing and maintaining bought-іп supplies of methane and oxygen.
Various attempts have been made to identify chemicals which will either inhibit the extent of corrosion beyond the required passivation layer, or selectively, inhibit the mechanism of corrosion product release by modifying the structure and adherence of the oxide film. A further possibility is the use of chelating reagents to continuously and selectively remove active species by dissolution from deposited material and oxide films. Such soluble species could then be removed on an ion exchange bed possibly with regeneration of the chelating agent.
Both of these approaches are under development and will have to be proved effective and acceptable to the existing complex primary circuit chemistry before they can be recommended for use by reactor operators.
Ail the magnox stations except Wvlfa use cooling t‘■akh about 6 m deep for spent fuel storage in Tip’- tor a minimum ot some three months before Tspateh, this allows the post-irradiation heat and radiation to decay to an acceptable level. Water is a cheap and elfective medium for cooling and shielding whilst allowing the handling operations to be observed.
A typical sequence of events is shown diagramma — tically in Fig 2.29, which shows the irradiated fuel handling and storage arrangements at Oldbury. There are essentially three basic routes depicted on the diagram; the incoming flask and skip route (stages /-6), the outgoing irradiated fuel route (stages 7-17) and the splitter flask route (stages 18-26).
A brief description of the facilities required and the 26 stages shown on Fig 2.29 is given as follows:
Incoming flask and skip
1 An empty skip arrives inside a road transport flask.
2 The flask is transferred to the storage bay by the flask crane.
3 When required, the flask is transferred to the washdown bay where it is washed, the lid bolts removed and the lid jacked open.
4 The prepared flask is transferred into the dispatch bay of the cooling pond: the lid is removed and returned to the decontamination bay, and the empty skip is removed from the flask and transferred to the pond storage bay by the skip crane.
5 Flask lid seals are inspected, if defective, the lid is decontaminated and transferred to the leak testing bay where seals are renewed.
6 When required, the empty skip is transferred to a pond handling bay.
Outgoing irradiated fuel route
7 Fuel elements and bottles discharged from the reactor arrive in the unloading tray in the cooling pond. From here they are transferred to a storage skip by manipulators.
8 When full, the skip is moved to the pond storage bay for a cooling period.
9 After cooling (for at least 90 days), the skip is returned to the pond handling bay w’here elements are removed to check that the correct cooling period has elapsed.
10 Polyzonal fuel elements are desplittered and placed in a second skip. Herringbone fuel elements are not desplittered and are placed in a separate skip,
11 When a skip is ready to leave the pond, it is transferred to the caesium sampling position in the storage bay.
|
|
|
|
A Road Transport Flask containing an empty Fuel Element Skip arrives at Oldbury on a Low Loader and is transferred to the Storage Say by the Flask Crane.
When the Flask is to be processed it is transferred to the Washdown Bay for a Pre-Ponding Wash. The Lid Bolts are removed and the Flask Lid is jacked open.
After cleaning and preparation the Flask is transferred to the Despatch Bay in the Cooling Pond by the Flask Crane.
Once the Flask is in the Cooling Pond the Lid is removed and transferred to the Washdown Bay and the empty Skip inside the Flask is removed and transferred to a Storage Bay by the Skip Crane.
The Lid Seals are visually inspected ready for replacement on the Flask. If the Seals are seen to be defective the Lid is decontaminated and transferred to the Leak Testing Bay where the Seals are renewed.
When the empty Skip is required it is transferred to a Handling Bay.
Fuel Elements and Bottles discharged from the Reactor pass through the Unloading Well equipment and arrive in the Unloading Tray in the Cooling Pond. From here they are removed by manipulators and placed in a Storage Skip.
When the Skip is full it is moved to the Storage Bay by the Skip Crane and left to cool.
After the necessary cooling period has elapsed (at least 90 days) the Skip is brought back into the Handling Bay.
Polyzonal Fuel Elements are removed from the Skip, monitored to check that the correct Cooling Period has elapsed, Desplittered and placed in a second Skip. Herringbone Fuel Elements are monitored but not Desplittered and are put in a separate Skip.
Once a Skip is ready to leave the Pond it is transferred to the Caesium Sampling Position in the R1 Storage Bay.
When the Skip is ready to leave the Pond it is checked under the Caesium Sampling Hood and then placed inside an empty Flask in the Despatch Bay.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12 Caesium sampling complete, the skip is placed inside an empty flask in the pond dispatch bay.
Note: At Sizewell A and Hinkley Point A, the skip
is removed from the pond up a shielded ramp before being placed in a flask, but the arrangement at Oldbury is more representative.
13 The flask crane collects a flask lid from the decontamination bay, lowers it onto the flask and returns the flask and its lid to the decontamination bay (see Fig 2.30).
14 The flask is decontaminated and the lid is bolted down. Health physics check for satisfactory decontamination and the flask is transferred to the leak testing bay.
15 The flask is leak tested, nitrogen purged and, if necessary, fluoride dosed.
16 The flask is transferred to the storage bay to await road transport and a final contamination check.
17 Transfer to road transport for delivery to reprocessing plant.
Splitter flask route
18 Splitter flask full of magnox debris.
19 Full splitter flask deposited on a cradle in the dispatch bay.
20 Flask and cradle transferred to the washdown bay for decontamination.
21 Decontamination flask and cradle transferred to the splitter flask transporter for delivery to the active waste dump loading bay.
22 Splitter flask removed from transporter and cradle and lowered onto a magnox debris vault door by the dump crane.
23 Magnox debris emptied into the vault and the empty flask returned to its cradle and transporter.
24 Splitter flask and cradle transported to flask crane.
25 Splitter flask and cradle transferred to the pond dispatch bay.
26 When required, splitter flask is removed from cradle and transferred to the pond handling bay, next to the desplittering machine.
Whilst ponds provide convenient shielding, careful
and rigorous water treatment and pond management
is necessary if magnox fuel can corrosion and re
lease of contamination are to be acceptable. The decay heat also has to be removed. Ponds therefore are provided with water circulating systems embodying filters, coolers and water treatment equipment. Contamination is removed by the filter and water treatment media and hence there is supplementary shielding provision for the exchange and storage of these arisings. Early experience with storage ponds was unsatisfactory, particularly when storage periods were excessive. Can-corrosion occurred and contamination spread from the water surface and from equipment as it was moved in and out of the water. Considerable ingenuity by station and other staff was necessary to cope with the difficulties.
It was these difficulties that led to the adoption of dry spent fuel storage at Wylfa (Fig 2.31). Each dry store cell consists of a bundle of vertical thimble tubes with a carbon dioxide atmosphere in w’hich the spent fuel is placed by the charge machine. The outside of the tubes is cooled by natural convection air. After the decay period the elements are discharged using a separate hoist to a shielded vault where they are de- lugged, placed in skips and dispatched in the transport flask. Subsequently, further dry storage has been provided at Wylfa in low head air-cooled vaults.
2.3 Reactor charge/discharge In principle, refuelling consists of coupling the pressurised FM to the reactor, removal of the spent fuel elements one at a time from the selected channel and subsequent charging of the new elements.
5.5.1 Types of measurement
The measurements fall into two main categories:
• Condition monitoring to monitor the chemical constituents that are critical to corrosion of and deposition on metal and graphite components.
• Indication of gross effects such as the ingress of water into the reactor caused by boiler leaks.
5.5.2 Condition monitoring
Lists of magnox reactor gas analysis measurements indicating duty, typical ranges and type of measurement are shown in Table 2.I2.
Helium is added to the coolant gas and its measurement is used to indicate coolant leak rate. The measurement of nitrogen indicates air ingress that may occur during refuelling operations, whilst the measurement of hydrogen may indicate oil in-leakage (hrough the gas-circulator gas/oil seal. Hydrogen, carbon monoxide and methane are effective condition
monitoring measurements with respect to graphite and/or steel corrosion, these factors being more critical for the AGRs because of the increased temperatures and coolant pressures.
Typically for condition monitoring purposes, a magnox station may use a katharometer and/or flame ionisation gas chromatograph with a local integrator/ controller arranged to sample each reactor in turn and provide a data printout every 30 minutes. Calibration gas mixtures are used to provide standards which have been checked against research laboratory standard mixtures.
The equipment used to place the viewing device at the various inspection positions inside the reactor may be divided into hoist units and units that move the viewing device out sideways once access has been obtained from the inspection penetration.
Hoist units form part of the inspection equipment of all AGRs and are used where gravity, together with a combination of fixed and temporary guides, can be utilised to insert the viewing device to the required position. In these cases the viewing device is lowered on a metal flexible hose which carries the cooling gas and the weight of the viewing device and any attachments; it also houses the electrical cabling required for services, control and telemetry of the viewing device. A typical hoist unit is shown in Fig 2.103, working in conjunction with an articulated TRIUMPH camera.
In order to inspect the relatively large area above the gas baffle dome and below the vessel roof, there is a requirement to traverse the camera horizontally once it has been lowered through the 7 m long small diameter (105 to 260 mm) access penetration. The first manipulator designed and developed for inspecting this area was for Hinkley Point B. It is capable of lowering the camera (housed within a 10 ш mast) through a 260 mm diameter peripheral fuel channel into the reactor, extending a telescopic boom horizontally up to 5 m and subsequently lowering the camera on its service hose to a further depth of 13 m, Additionally the whole machine is capable of slewing through 360°, can elevate or lower the telescopic boom and is fitted with a knuckle joint at the end of the boom to pivot the camera up through the horizontal. Figure 2.104 shows the general arrangement of the manipulator.
Fig, 2.101 Arrangement of boiler closure viewing equipment
ED OVPACT POlLEV |
Fig. 2.І02 Boiler tube viewing equipment |
Aboe-dome manipulator at Hlnkley Point В
At Dungeness B, the only available access penetration for viewing the above-dome region has a diameter of 170 mm. This restraint has led to the concept of the ‘links manipulator* where a ‘break-back* chain is used to feed the camera into the reactor and the chain itself forms the boom of the manipulator. This principle has been extended to cover inspection requirements for Hartlepool, Heysham 7, Heysham 2 and Torness. Fig 2.105 shows the Heysham 2 interstitial manipulator which is an example of the ‘links’ principle. For Hartlepool and Heysham 7, a manipulator has been built which has a boom extension of up to 7 m; it has five movements of freedom — slew, elevation, extension plus ‘wrist and knuckle’ at the boom tip.
The various motions of these manipulators are pushbutton-controlled from a central console and there is also a microprocessor-based ‘teach and repeat* control system to allow semi-automatic control. All manipulators are filled with hand drive facilities for emergency retrieval in case of power failure.
A variant of the links idea is used to deploy cameras from penetrations in the bottom of the pressure vessel. For these routes, the links are stored on a drum and they are driven up the standpipes to get across either to the boiler annulus (Heysham 2) or into the undercore region (Hartlepool/Heysham 7). For the former, the viewing angle of the camera is extended by using the combined ‘wrist and knuckle* action of a drive head fitted to the end link.
In addition to the above, boom manipulators have been developed to view the under-boiler region (Hink — ley Point B), outlet duct viewing (Hartlepool/Heysham 7) and the sub-diagrid region (Heysham 2) using the access available when a gas circulator is removed. For the first two, the boom consists of a series of tubes that are screwed together and extended from the access position. For the latter, a telescopic rectangular section boom can be extended from the access position and the camera viewing angle extended by using the combined ‘wrist and knuckle* action of a drive head fitted to the end of the boom.
This system is provided to protect the boilers against the ingress of chloride from the CW system or caustic solutions from the condensate polishing plants. A high level of protection is required and thus, as far as practicable, two diverse sets of equipment are provided, each using ‘2 out of 4’ logic.
9.11 Heating and ventilating system
There are over 50 separate heating and ventilating systems on Heysham 2, of which about 40 are related to safety and/or contaminated zone systems. Considerable effort has been put into ensuring that the standard of C and I design and equipment on these systems is of a comparable level to that employed on the main reactor/turbine-generator plant.
A number of systems are controlled by programmable logic controllers (PLC) also known as Programmable Controllers (PC), which implement both sequential and modulating control. These PLCs are linked to a microprocessor, programmed in Cutlass, which provides centralised logging and display.
Table 2.15 Typical AGR tripping schedule
|
T BLE M 5 want’d) Typical ACR mppins schedule
Trip parameters |
Trip vetting nominal |
Redundancy |
Comments |
pucrse ■iiuirdline 1 Hi eh. COO temperature rate and level ‘top |
identical to item 9 — main guardlme |
2 out of 4 |
|
‘ £■ v C" fiuv 1 l. r’car ^ "uггr.-1 rate and level stop |
Identical to item 3 — mam guardiine |
2 out of 4 |
|
1 Quadrant trip initiated |
— |
2 out of 4 |
|
Auxiliary guard line 1 Pulse count rate high |
500 kW |
2 out of 4 |
|
Quadrant protection 1 Hall-unit outlet gas temperature high How |
з:о°с 270°C |
2 out of 3 per halfunit into 1 out of 6 per quadrant |
Safety associated |
2 Low superheater transition joint metal temperatures |
See Note l |
2 out of 3 per halfunit into 1 out of 6 per quadrant |
|
3 Circulator underspeed/overspeed |
2520 r/min 3220 r/min |
2 out of 3 per circulator into 1 out of 2 per quadrant |
Safety associated |
4 Differential oil pressure across circulator bearings very low |
0.75 bar |
2 out of 3 per circulator into 1 out of 2 per quadrant |
|
5 Oil level from circulator compartment very high |
See Note 2 |
2 out of 3 per circulator into 1 out of 2 per quadrant |
|
6 Circulator lub oil tank level very low |
See Note 2 |
2 out of 3 per circulator into 1 out of 2 per quadrant |
|
і Circulator high differential pressure between reactor and motor compartment |
4 bar |
2 out of 3 per circulator into 1 out of 2 per quadrant |
|
й CACS demineralised water temperature high |
40°C |
2 out of 3 per quadrant |
Safety associated |
9 Circulator outlet gas temperature high |
435°C |
2 out of 3 per circulator into 1 out of 2 per quadrant |
|
SSD initiation |
|||
Bulk group 1 insertion |
691Щ |
||
Delay timer L. |
4.35 s |
Votes |
I Гпр -.cuing is a function of steam pressure — trip is based on integral level switches with fixed setting
‘ Q = quiescent
There is now an increasing awareness of the potential for common mode failures arising from shortcomings or defects both in plant design and in subsequent manufacture, installation and operation. There is no agreed mathematical method of calculating a value for the limiting effects of common failure on system reliability. There is, however, agreement that systems with identical redundant channels should not be assumed to be capable of achieving reliabilities better than about 10”4 to 10”s per demand. This limitation is applied even though random failure rate data might indicate a lower failure probability.
The design safety guidelines issued by the CEGB specify a protection system reliability of better than 10~4 failures per demand for faults which are postulated to occur at frequencies of 10”3 per year or greater. To design a system to meet these stringent requirements has required the specification of two diverse protection systems each with four-way redundancy. For the PWR it was decided to base one system on multiple distributed microprocessors with digital processing, and the other on the well proven Laddie guard lines with analogue trip amplifiers as used on existing magnox and AGR stations.
The microprocessor system does employ core logic for the guard line voting, but the two systems are sufficiently different in design and hardware to avoid common mode effects.
The two systems are referred to respectively as the primary protection system (PPS) and the secondary
protection system (SPS).
The safety case for the station is made on the basis that the PPS and SPS each independently provide protection for all frequent faults (frequency of 10~3 per year or greater). The PPS provides protection for all faults (frequent and infrequent) that are within the station design basis, and two independent parameters are generally available to detect each fault.
The primary and secondary protection system have measurements of almost identical parameters from which to generate reactor trip and ESF action. The instrumentation used for the measurements in each system is chosen to be as diverse as practicable within the limitations of the transducers available.
An example listing of the parameters that are measured for trip protection purposes for the two systems is given in Table 2.17.
The primary protection is implemented with microprocessors and is therefore able to provide for an extensive range of parameters and functions with complex logic. The use of microprocessors permits protection to be derived using algorithms to assess limiting core conditions dependent upon control rod positions and operating power levels. This protection would not have been possible using analogue based equipment without excessive complexity.
Axial macroscopic
At the start of a magnox reactor’s life, the uniform fuel loading leads to a flux (and hence rating) shape similar to the theoretical cosine shape of a uniform bare reactor, but with some distortion caused by the partially inserted regulating rods. A typical magnox axial flux (and rating) shape is shown on Fig 3,5. As burn-up proceeds the competing processes of U-235
RELATIVE ELUX Fig. 3.5 Axial flux distribution on a magnox reactor |
burn-up and Pu-239 build-up result in a slight increase in peaking of the rating shape followed by a degree of flattening. The changes in ratio of peak — to-mean axial rating are however only a few percent, considerably less than the effects caused by rod bank movements during normal reactor operation.
In magnox reactors the radial flux shape is flattened by the use of neutron absorbers. A typical average radial macroscopic rating shape is shown on Fig 3.6 (a). This shape, dearly showing the large flat central region, is maintained throughout core life. Superimposed on this shape is a local channel-to-channel variation due to variation in isotopic content of the fuel. The power generated in a newly refuelled channel rises relative to its surroundings as plutonium builds up until the loss of U-235 begins to outweigh the increase in Pu-239. This behaviour is demonstrated on Fig 3.7, which shows the ratio of individual channel power to surrounding channel power, known as the ‘age factor’, for a typical magnox reactor. Of the lO^o or so increase in relative power, the dominant effect is the increase in fission cross-section with a
small {less than 2%) contribution due to the higher heat generation per fission of plutonium. The changes occurring in the channel flux level relative to its surroundings is small (less than 1%). This constancy of flux level arises because the channels are close together relative to neutron migration lengths and hence the neutron flux in the channel derives mainly from neutrons produced in surrounding channels which, because of the on-load refuelling in magnox reactors, are (on average) under constant conditions when the fuel cycle has reached an equilibrium state.
If an abnormal situation is detected with the reactor at power, requiring rapid shutdown, all the control rods are dropped into the core to shut down the reactor, the safety rods are then withdrawn (when it is deemed safe to do so). Safety rods provide a reserve of negative reactivity which can be dropped into the reactor core if an abnormal situation is detected while the reactor is shut down.
In most magnox reactors this function is provided by a group of black rods, 10-20 in number, specially designated for this duty, and these rods are normally held fully withdrawn at all times. At Dungeness A, safety rods were originally provided, but these have now been incorporated into the bulk groups and the satetv function, while shut down is provided by the regulating rods and trim rods. At Wylfa, the last of the magnox series, no safety rods are provided because the complement of other rods is deemed to be adequate to ensure safety at all times.
In AGRs the safety rod function is provided by some of the grey rods while the reactor is shut down. Prior to start-up the safety group are lowered to the same height as the remaining grey rods.
Safety rods are not formally claimed to provide protection in any faults, and the reactivity margin at shutdown does not depend on safety rods.
Secondary shutdown rods
In magnox reactors with steel pressure vessels some bulk rods, typically 25-40 in number and designated secondary shutdown (SSD) rods, are fitted with a mechanical latch which releases the rod from its supporting wire or chain in the event of a rapid gas depressurisation, to ensure a rapid shutdown of the reactor. In all other respects the rods operate as bulk rods, and in normal operation an SSD rod is indistinguishable from other bulk rods.