The technical requirements (TR) document is where the owner specifies the technical requirements applicable by the supplier to the plant design, licensing, procurement, construction, commissioning, operation and maintenance, and which shall be taken into account by the bidders in the preparation of their bids.
The main topics addressed in the TR document are as follows:
• Applicable codes, standards and regulatory requirements
• Licensing requirements and procedures
• Site data, including geography and topography, geology, geotechnical and seismic information, methodology and environment (including site ambient and cooling water temperatures and humidity), demography, site access
• Design criteria and requirements for all project disciplines (e. g. civil — structural, mechanical, electrical, instrumentation and control, radiation protection, nuclear safety)
• Material requirements
• Requirements and specifications for plant structures, systems and equipment
• Power grid requirements
• Construction and erection
• Plant operation and maintenance
• Nuclear fuel requirements, including length of fuel cycle, spent fuel storage, refuelling operations
• Plant simulator requirements
• Personnel training.